Around 100,000m³ of sand will be removed from key waterways in the Hawks Nest and Tea Gardens area, including the Lower Myall River, Corrie Channel, and Eastern Channel.

The sand will be stockpiled at the end of the Winda Woppa peninsula and later used to replenish Jimmys Beach after erosion events.

The dredging work, carried out by contractor Dredging Solutions, is expected to start in early March and finish by late October, weather permitting.

The proposed dredge area

240830 Plan Showing Proposed Dredge Areas and Volumes CAD-A3 23090B REV 2

Plan Showing Proposed Dredge Areas and Volumes

The Myall River dredging project is fully funded by Transport for New South Wales through the NSW Boating Now Program