News

June - August update

29 July 2025

  • Works Completed June / July 2025

    • Essential Energy power connection, pole removal Wynter / Combined St.
    • Complete cross girder beams and restraint blocks
    • Complete deck pour 1-7 July, 2 and 3 16-17 July respectively
    • Commence F-Type barrier
    • Commence of site manufacture precast parapets
    • Commence offsite manufacture steel rails
    • Adjust traffic arrangement Wingham Rd to allow for bridge approach works
    • Completion of drainage lines to Combined / Wynter St
  • Works Planned July / August 2025

    • Complete deck pour 4 and 5 24 July 2025
    • Commence link slab pour 1-4
    • Complete footpath slabs 1-5
    • Commence Pour RW1 & 2 F-Type barrier
    • Pour approach slabs A and B
    • Strip headstocks 1-4, complete defects inspections and repairs
    • Demobilise pier/headstock scaffolds
    • Establish Earthworks repatriation underbridge and final scour protection.
    • Complete general fill and commence UZF earthworks to approach roads