May - June 2025 update

19 May 2025

Works Completed April / May 2025

  • Timeline item 1 - complete

    Abutment A/ RW1 back fill

  • Timeline item 2 - complete

    Abutment B / RW2 back fill

  • Timeline item 3 - complete

    Piers 1-4 Columns and Headstock including mortar pads.

  • Timeline item 4 - complete

    Girder casting, crack repairs and transport to Cundletown

  • Timeline item 5 - complete

    Girder delivery, dressing & installation commenced

    Halted due to rain and creek level: repositioned crane and rescheduled lifting sequence.

  • Timeline item 6 - complete

    Final under bore Wynter St

Works Planned May/ June 2025

  • Timeline item 1 - active

    Girder placement (30), temp propping

  • Timeline item 2 - active

    Cross girder beam FRP

  • Timeline item 3 - active

    Cast girder restraint blocks

  • Timeline item 4 - active

    Earthworks to adjust temp detour route in preparation for road tie in works

  • Timeline item 5 - active

    Essential Energy power connection, pole removal.

  • Timeline item 6 - active

    Completion of drainage lines to Combined st