September - October update

29 September 2025

  • Works Completed July / August 2025

    • Complete bridge structure
    • Complete bound subbase to north and south road
    • approaches
    • Prime seal ready for concrete annulus
    • Complete precast concrete parapet installation
    • Delivery of twin rail steel barriers to site end Sept
    • Completion delayed by stormwater defect rectification
  • ​Works Planned September / October 2025

    • Stabilised pavement construction
    • kerb and channel works to roundabout start
    • Installation of bridge railings and guardrails
    • Asphalt pavement and line marking,
    • Signage footpaths and landscaping