The contractor mobilised at the beginning of March and has been working on the site labelled on the dredging map as BND-04 It is nearing completion on that point and then moving upriver to BND-03. It will then move on to 02 and 01 as each is completed.

This will mark the completion of Myall River. It will then move to the Corrie Channel to work on BND-05 then to the Eastern Channel to work on BND-07

Overall completion is due on 31 October.